CITY of RAPID CITY Agenda Item Summary |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Public Works Committee Meeting Date: 9/9/2014 |
City Council Meeting Date: 9/15/2014 |
||||||||||||||||||||||
Staff Contact: Dan Coon |
Petitioner: |
||||||||||||||||||||||
Location: Water Reclamation Facility |
|
||||||||||||||||||||||
Agenda Title: |
|||||||||||||||||||||||
Approve Change Order No. 1F to MAC Construction Company, Inc. for WRF Algae Control Improvements, Project No. 14-2158/CIP No. 50971, to increase the Contract Time 2 days with no change in contract price. |
|||||||||||||||||||||||
Summary: |
|||||||||||||||||||||||
Delivery of critical materials, which was beyond the Contractor’s control, was delayed. Contractor needed 2 additional days to substantially complete the project. Project was substantially complete on August 4, 2014. |
|||||||||||||||||||||||
Funding Source & Fiscal Impact (if applicable): |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Recommendation: |
|||||||||||||||||||||||
Action: Approve Notes: |
|||||||||||||||||||||||
City Council Options: |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Attachments & Links: |
|||||||||||||||||||||||
|
|
||||||||||||||||||||||
|
|
|
|||||||||||||||||||||
|
|
|
|||||||||||||||||||||